A certain company has 50 printers that print at the same constant rate. Working continuously and simultaneously at that rate, it takes 9 of the printers 5 hours to complete print job A. Working continuously and simultaneously at that rate, it takes n of the printers 3 hours to complete print job A.
Quantity A
n
Quantity B
16
B显示答案